Correct Answer : B
Explanation :
Explanation :
Ram = 12×7=84h, Shyam = 8×9=72h. Work = 1. Ram rate=1/84, Shyam=1/72. Together per hour=1/84+1/72=13/504. Per day (7h)=91/504. Days=504/91=72/13.
Correct Answered :
Wrong Answered :