1. Statement (I): Cross drainage structure, aqueduct is constructed to negotiate an aligned channel over, below or at the same level of a stream.

Statement (II): Aqueduct is constructed, when full supply level (FSL) of canal is much higher than high flood level (HFL) of a stream.


A

Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I)

B

Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)

C

Statement (I) is true but Statement (II) is false

D

Statement (I) is false but Statement (II) is true

Cross Drainage Works J.E Civil 2023
Correct Answer : A
Explanation :

Both statements are true and Statement (II) correctly explains Statement (I). Aqueduct is built when canal FSL is above stream HFL.

Correct Answered :

Wrong Answered :

CONTACT US

  • J & K

  • admin@prepmart.in

  • LIKE AND SHARE YOUR EXPERIENCE

    Like Us on Facebook Join Us on Telegram
    VISITORS COUNT 1 1 3 2 0 5 7
    Developed By : PrepMart