1. The expected time (E) of a PERT activity in terms of optimistic time (O), pessimistic time (P) and most likely time (M) is given by

A

E = (O+2M+P)/3

B

E = (O+4M+P)/3

C

E = (O+2M+P)/6

D

E = (O+4M+P)/6

PERT J.E Civil 2023
Correct Answer : D
Explanation :

Expected time in PERT is given by E = (O + 4M + P)/6.