Civil Engineering MCQs

General Civil Engineering Questions with solutions MCQs

1. Which of the following traverse adjusting methods is employed for angular measurements?

A

Transit method

B

Graphical method

C

Bowditch`s method

D

Axis method

General Civil Engineering JE Civil 27 Oct 2021 (Shift 2)
Correct Answer : A
Explanation :

Option A is correct as per standard civil engineering principle.

Correct Answered :

Wrong Answered :

2. When perimeter is less than time, discharge is:

A

Same

B

More

C

Less

D

Zero

General Civil Engineering JE Civil 27 Oct 2021 (Shift 2)
Correct Answer : B
Explanation :

Option B is correct as per standard civil engineering principle.

Correct Answered :

Wrong Answered :

3. The immediate predecessors of activity D are A, B, and C. Given the earliest finish time of activity A, B and C are respectively 10, 12 and 16 days, the earliest start time of activity D will be:

A

10 days

B

12 days

C

38 days

D

16 days

General Civil Engineering JE Civil 27 Oct 2021 (Shift 2)
Correct Answer : D
Explanation :

Option D is correct as per standard civil engineering principle.

Correct Answered :

Wrong Answered :

CONTACT US

  • J & K

  • admin@prepmart.in

  • LIKE AND SHARE YOUR EXPERIENCE

    Like Us on Facebook Join Us on Telegram
    VISITORS COUNT 1 1 3 1 6 3 0
    Developed By : PrepMart