1. Match the list-1 with list-2 and select the correct answer using the codes given below.
List-1 (Description): List-2 (Purpose details or functions):
a. Estimation, 1. Setting objectives and determining a course of action for achieving the project objectives.
b. Planning, 2. The science of calculating the different load requirements so that proposed structure can withstand worst-case scenarios.
c. Quality control, 3. To ascertain the probable cost of a proposed project.
d. Designing 4. Testing units and determining whether the materials are within the specifications for the final product.
Project Functions
J.E Civil 2023
Correct Answer : B
Explanation :
a-Estimation → cost (3), b-Planning → objectives (1), c-Quality control → testing (4), d-Designing → load calculations (2). Correct code: 3 1 4 2.